A biomass briquette producer in Cuba ordered a production line with a target capacity of 1.5-2 metric tons per hour. The project was planned around a three-phase 460V, 60Hz site supply and a customer-approved layout envelope of 22,000 × 8,000 mm. The buyer visited the workshop and observed the briquette press running before shipment. The equipment was packed into one 40-foot container and one 20-foot container for delivery to Mariel Port.


Overview of the biomass briquette production line for the Cuba project.
1. Cuba Project Overview and Confirmed Requirements
The buyer's confirmed project information included the target production range, the site's electrical supply, the available floor area and the required discharge arrangement. These items were used as the basis for the preliminary equipment selection and layout work.

2. How the 1.5-2 T/H Line Was Configured
The Biomass Charcoal Briquette Making Machine establishes the target forming rate. The crusher must prepare material at a compatible rate and particle size, while the rotary dryer must be selected according to the amount of water that needs to be removed. Screw conveyors, bucket elevators and the discharge arrangement are then coordinated with the process flow and the approved building layout.
Biomass Rod Brick Press Machine selection: FTZBJ-2500
The FTZBJ-2500 is the model in the supplied range whose stated output of 1.5-2.2 t/h covers the project's 1.5-2 t/h target. Its main motor is listed as 55/75 kW, its briquette diameter range is Ø80-Ø100 mm, and its feed screw is Ø219 × 5,000 mm.
The three auxiliary power figures in the feed column are shown in the order supplied: feed screw, forced feeder and lubrication pump. The supplied technical data also lists a finished briquette density of 0.7-1.3 g/cm³ and a calorific value of 3,000-5,500 kcal. These values should be treated as stated product data; the test method, material basis and calorific-value basis should be confirmed before using them as guaranteed product specifications.

3. Crusher Capacity and Raw Material Size
The supplied crusher range contains six models from 7.5 kW to 110 kW. The project electrical drawing identifies a 30 kW main crusher motor. The listed 30 kW model has a rated capacity of 2,000 kg/h and a maximum feed size of 200 mm.
The 2,000 kg/h rating of the MK-600 matches the upper end of the line's 2 t/h target on paper. It does not, by itself, prove that the crusher will sustain 2 t/h under every raw-material condition. Material species, bulk density, moisture, feed consistency, screen size and operating hours can affect actual throughput. A continuous-line capacity test or a documented engineering allowance should be reviewed before describing the crusher as having spare capacity.
The crusher's listed maximum feed size is 200 mm, while the supplied press information describes a 1-10 mm material size for pressing. The crushing stage therefore has to reduce the incoming material to the particle-size range required by the downstream process. Confirm the 1-10 mm specification and the screen configuration against the final process specification.

See the sawdust crusher range for the available crusher models.
4. Rotary Dryer Selection Based on Moisture Removal
The supplied rotary dryer range includes ten drum sizes, from 0.8 × 8 m to 1.8 × 17 m. The listed power column contains two separate figures for each model: the drum drive power and the fan power. They are reproduced as separate ratings and are not added together here.
Dryer selection should be based on the water-removal duty, not only on the line's hourly material throughput. The engineering calculation needs the actual wet-basis inlet moisture, target outlet moisture, dry-solids flow rate, material properties, operating temperature and expected heat losses. The project information mentions an inlet moisture range of 12%-18%, but it does not provide a confirmed outlet moisture target or a calculated evaporation load.
Rotary dryer and cyclone separator.
5. Conveyors, Elevators and Complete Line Matching
Screw conveyors and bucket elevators connect the receiving, crushing, drying and briquetting sections. Their dimensions and drive ratings should be selected to suit the material flow, elevation changes, transfer points and the press feed arrangement. The supplied project information identifies a 3 m discharge rack for the final discharge section.
A production line is only as consistent as the interaction between its stages. The press model provides the forming-capacity reference; the crusher must handle the incoming feed and deliver the required particle size; the dryer must meet the moisture target; and the conveyors must transfer material without creating a bottleneck. The final line rating should be confirmed from the complete process design rather than by adding individual machine nameplate capacities.
6. Custom Plant Layout and Electrical Design for Cuba
Two project drawings were prepared: a plant layout within a 22,000 × 8,000 mm floor envelope and an electrical drawing based on the stated three-phase 460V, 60Hz site supply. The layout was used to coordinate the drying, briquetting and finished-product areas before the machines were positioned.
The supplied layout description identifies a plan view for floor marking, a section view for checking clearance above the rotary dryer, and an elevation view for the finished-product area. The listed equipment on that drawing includes a receiving hopper, screw conveyor, bucket elevator, rotary dryer, cyclone separator, hot-air furnace, briquette press and a 3 m discharge rack.

Electrical supply: resolve the drawing and site ratings before connection
The project brief specifies a three-phase 460V, 60Hz site supply. However, the separate crusher circuit drawing is described as showing 480V and 440V, both at 60Hz, together with a 30 kW main motor and a 1.5 kW lubrication pump. These voltage references are not identical. They must be checked against the final motor nameplates, electrical bill of materials, control-panel drawings and the actual site supply before installation or energization.


Crusher circuit drawing.
7. Factory Run Observation and Customer Inspection
Before shipment, the buyer's group visited the workshop and observed the bio briquettes manufacturing machine running with raw material. A finished briquette was removed during the run and inspected by hand for its visible surface and diameter.
The available project record documents an observed factory run and a visual, hands-on inspection. It does not include instrument readings, a measured production-rate report, a laboratory test, or a third-party acceptance certificate. For that reason, this case study describes what the buyer observed and does not present the visit as a certified capacity test.

If a commissioning report, measured output record or product laboratory report becomes available, it can be added as a separate evidence item with the test date, raw material, moisture content, operating settings, measurement method and results.
8. Export Packing and Shipment to Mariel Port
The production line was arranged for shipment in one 40-foot container and one 20-foot container to Mariel Port, Cuba. The supplied packing description states that the rotary dryer drum sections were loaded first, followed by the press frames and then motors, pipes and smaller components. Components were wrapped to protect painted surfaces and machined ends during handling.
- Drum sections: The rotary dryer sections were loaded as separate sections.
- Frames: The briquette press frames were positioned to match the available container space and the loading plan.
- Motors, pipes and accessories: Smaller components were wrapped and packed after the larger assemblies.
The project description lists two wear-part items in the spare-parts package: nozzles and forming sleeves. Confirm the exact English names and quantities against the packing list before publication, because terminology for press wear parts can vary by machine design.



The receiving team should prepare a suitable unloading area, lifting equipment rated for the heaviest component, a clear route to the installation zones and temporary storage space for the dryer sections. The actual lifting points, component weights and unloading sequence must follow the final packing list and lifting instructions.
9. Information Needed for a Similar Biomass Briquette Line
A reliable quotation for a biomass briquette production line requires more than a target tonnage. The following information helps the engineering team evaluate the press, crusher, dryer, material handling equipment, electrical configuration and plant layout.
- Target capacity and operating hours: State the required tons per hour and planned operating hours per day. Daily output depends on both rated throughput and actual operating time.
- Raw material and storage: Identify the biomass type and whether it is stored indoors or outdoors.
- Moisture content: Provide the measured inlet moisture and required outlet moisture. Confirm whether percentages are reported on a wet basis or dry basis.
- Particle size: Provide the incoming material dimensions and the required particle size before briquetting.
- Power supply: Confirm voltage, frequency and phase from the factory's electrical supply documentation.
- Plant dimensions: Provide floor length, width, available height and the position of doors, columns and finished-product storage.
- Briquette requirements: Specify briquette diameter, shape, intended use and any required density or calorific-value standard.
Send your target capacity, biomass type, inlet and outlet moisture, particle size, briquette dimensions, site voltage/frequency/phase and available plant area. The engineering team can review the process stages and prepare a proposed equipment configuration and layout for your project.
Send Your Project Requirements10. Frequently Asked Questions About Biomass Briquette Production Lines
What is the target capacity of the Cuba biomass briquette line?
The target capacity stated for this project is 1.5-2 metric tons per hour. The selected FTZBJ-2500 press model is listed with a rated output of 1.5-2.2 t/h. Actual complete-line output depends on raw material, moisture, process settings and the capacities of upstream and downstream equipment.
Which biomass briquette press machine model was selected for the 1.5-2 t/h target?
The supplied press range identifies the FTZBJ-2500 as the model with a stated output of 1.5-2.2 t/h. Its main motor is listed as 55/75 kW and its briquette diameter range as Ø80-Ø100 mm. Confirm the final motor configuration and press specification against the signed order documents.
Why does the project use a 30 kW crusher?
The project electrical information identifies a 30 kW crusher motor. The MK-600 model in the supplied range is listed at 2,000 kg/h. This matches the upper end of the target line capacity on paper, so actual continuous throughput should be verified with the specified raw material and operating conditions.
Which rotary dryer model was used in the Cuba project?
The supplied project information lists ten available drum sizes but does not identify the final selected model. The correct dryer should be selected from the evaporation duty, using measured inlet moisture, target outlet moisture, dry-solids flow and material properties. The final approved equipment list should be checked before naming a specific model.
Was the whole line designed for 460V and 60Hz?
The project brief specifies a three-phase 460V, 60Hz site supply. The separate crusher drawing is described as containing 480V and 440V labels at 60Hz. These references need engineering reconciliation against the final motor nameplates and approved electrical drawings before the page can state that every machine is confirmed for the same voltage.
What plant space was approved for the project?
The approved layout envelope stated in the project information is 22,000 × 8,000 mm. The final arrangement should also account for machine maintenance access, dryer clearance, material transfer routes, doors, columns and finished-product handling.
Did the buyer test the production line before shipment?
The buyer's group visited the workshop and observed the briquette press running with raw material. A finished briquette was visually and manually inspected. The available project record does not include instrumented capacity measurements or a third-party test certificate.
How was the biomass briquette line shipped to Cuba?
The supplied project information states that the line was shipped in one 40-foot container and one 20-foot container for delivery to Mariel Port, Cuba. Confirm the actual bill of lading and packing list before publishing shipment dates or container numbers.
What is the stated delivery lead time and warranty?
The project information states a dispatch lead time of 15-25 days after advance payment and a one-year warranty excluding wear parts. This is the stated dispatch period, not an ocean-freight transit-time estimate.
Related equipment: Sawdust Crusher | Biomass Briquette Making Machine
Editorial note: This case study is based on the project information available at the time of writing. Confirmed machine configurations, final electrical ratings, dryer model, packing details and test records should be updated from the approved order documents before publication.