With the development of science and technology, aquatic feed equipment production lines have gradually realized automated production and improved production efficiency. However, in order to make the aquatic feed equipment production line play the best performance, some operation skills need to be mastered. This article will introduce the operation skills of aquatic feed equipment production line from the following aspects.
1. Equipment installation and commissioning
1. The installation of the equipment should follow the manufacturer's requirements to ensure that the equipment is stably placed on the horizontal plane. At the same time, it is necessary to ensure that the connection between the various components is firm to avoid falling off during use.
2. After the equipment is installed, the entire production line needs to be debugged. First, check whether the working status of each electrical component is normal, such as motors, electronic control systems, etc. Secondly, adjust the parameters such as the running speed and output of the equipment to achieve the best production effect.

 

fish feed processing line

 

Model Capacity(t/h) Power(kw) Screw Diameter(mm) Weight
75-B 0.3-0.4 22 80 1000
85-B 0.5-0.6 30 90 2000
90-B 0.6-0.7 37 100 2100
100-B 0.7-0.8 55 120 2200
135-B 1-1.5 75 135 3200


3. During the debugging process, pay attention to the operation of the equipment, such as abnormal noise, vibration, etc. If any problems are found, contact the manufacturer in time for processing.
2. Preparation and delivery of raw materials
1. The preparation of raw materials should be carried out according to the formula provided by the manufacturer to ensure that the quality and proportion of the raw materials meet the requirements. At the same time, the storage environment of the raw materials should be kept clean and dry to avoid moisture and deterioration.
2. When delivering raw materials, the principle of "gradual increase" should be followed. That is, a small amount of raw materials should be delivered for trial production first, and then the amount of raw materials delivered should be gradually increased after the equipment is fully operational. This can avoid equipment overload or failure during production due to too much raw materials delivered at one time.
3. When delivering raw materials, pay attention to controlling the delivery speed to avoid too fast a speed that causes the equipment to be unable to process the raw materials in time. At the same time, pay attention to observe the operation of the raw materials in the production line, such as whether there is any blockage. If any problems are found, stop the machine and clean it up in time.